LMRC COMPLETES THE TRACK LAYING OF DOWNLINE TUNNEL; TO COMMENCE METRO OPERATIONS VERY SOON IN THE UNDERGROUND SECTION

  • October 07, 2018

Lucknow Metro Rail Corporation (LMRC) has achieved another milestone while completing the work for the underground section between the K. D. Singh Stadium Metro station ramp & Charbagh Metro station ramp by completing the track laying work in the DOWNLINE tunnel. Track laying work in the UPLINE tunnel had already been completed and LMRC is planning to commence Metro operations very soon in the Underground section.

LMRC used the Mass Spring System (an elastomer pad of 25 mm thickness) below the track bed for construction of track. Mass Spring System, procured from Austria, eliminates the problem of vibration and sound in adjoining structures of the underground portion.

For the construction of track, first of all the Elastomer Mass Spring System sheet is laid, then reinforcement mesh is laid over this and then it is filled with concrete up to the rail bottom. Rails are wielded continuously to avoid any joint in the rails.

Besides track laying, Lucknow Metro has also completed almost 80% work of the Rigid Overhead Catenary System (ROCS) i.e. overhead electrification which is being carried out inside both the tunnels for traction power.

Apart from this, the work of entrance and exit gateways at all underground stations has almost been almost completed. More than 60% of tiling and beautification work at the concourse and platform area of all the three underground Metro stations (i.e. Hussainganj, Sachivalaya & Hazratganj) has also been completed. The construction work of all the important rooms related with Metro rail operations such as the Electrical, UPS, DV Room, Telecom & Security Room etc. is also being done at a fast pace.