LUCKNOW METRO

  • July 14, 2018

Sri. Kumar Keshav, Managing Director, Lucknow Metro Rail Corporation, today reviewed the development progress of Metro construction work under the North-South Corridor of Section (1B), with the working entity of Metro, starting his inspection; he first oversaw the ongoing construction work of KD Singh Metro Station which is being the first metro station of this section. The work of this metro station is at full pace with the work of framing, stairs, entrance and exit gates have done in their advance form.

The work of Metro Cantilever Bridge (45 Meters) going through Subhash Chandra Park has been completed with the installation of U-girders. Now the work of linking the two sides of the Special Cantilever Bridge is being done, which was further appreciated by the Managing Director who showing the satisfaction while seeing the work here.

The Managing Director, in his visit, also saw the work of the University and I.T. Metro Station, where he saw the work of making concourse slab with the work of entrance and exit etc. and the work of Second Special Cantilever Bridge(60 Meters) near Karamat College is also in full progress.

After this, The Managing Director also saw the ongoing works of the Badshah Nagar, Lekhraj, R.S. Mishra, Indiranagar and Munshipulia Metro Stations where he oversaw the work of making the staircase at all Metro stations which are in progress. From the Indiranagar Metro Station, on the top of the polytechnic flyover, the Metro has started work of its Cantilever Bridge, and the process of connecting this cantilever bridge with the metro pillar near the flyover is being done. The total length of this Bridge will be of 180 Meters.

Where on one side U-girder are installed which is also followed by the laying of tracks and OHE Mast in all elevated S of this section. The remaining work for keeping the U-Girder at the kukrail Nala, Polytechnic, Nishatganj, and IT crossing will start soon.